DAY3 OF FRAMING?Really!!

by LiveModern Webmaster last modified Jan 04, 2012 02:38 AM
Editorial Rating: 1 2 3 4 5
Average Rating: 1 2 3 4 5 ( 0 votes)
by TaC studios, architects last modified Mar 24, 2011



 

 

So the first day of Spring begins our 3rd day of framing, and look how far we have come baby. Foundation is complete,Pool is in, the grade has been worked around the foundation, the Big Garden wall footings are in, steel is in place, and half the framing is complete! With the wall panels delivered to the site very little time(=$$$) and wood (=$$) has been wasted. We have been fortunate with the weather in this phase. Since our start the 3rd of January, we have lost 23days to bad weather~so we are not doing so bad with our schedule. All our rough plumbing  &  electrical are ready for install, and our roofers are standing by.......can't wait to see where we are on the 7th day of framing! Thank goodness for Builder1st Source!


 

 

 
 
 