It's been a while since we posted but there was not much to chat about. We had a delay due to the City of Toronto and the sewer people. After spending 10k (rip off) on a new sewer line the client was rewarded by late response times and no shows.
But we are back and the project is moving forward once again. The sewer is in, the electrical, mechanical and plumbing rough-ins are done and the polished concrete floors are scheduled to be poured this Saturday!!!
The Metal stairs and railings have already been made so after the floor is poured the rest of the house will move along at a fast pace.