casita framing is happening at a fast pace

by LiveModern Webmaster last modified Oct 29, 2012 01:06 AM
Editorial Rating: 1 2 3 4 5
Average Rating: 1 2 3 4 5 ( 0 votes)
by Mark Meyer last modified Oct 28, 2012

After a slow start to the foundation pour, framing has sprung up on the slab of the 850s.f. 2/2 guest house. By the end of the next week it should be all dried in and siding and roofing going on....




 

 

After a slow start to the foundation pour, framing has sprung up on the slab of the 850s.f. 2/2 guest house. By the end of the next week it should be all dried in and siding and roofing going on.

IMG_1402

 

End of day one saw wall layout and framing and the floor trusses in place.

IMG_1403

End of day 2 saw upper floor decking, wall layout and framing, stair construction, lower wall sheathing, and steel header fab and install at the upstairs roof deck.

IMG_1404

 

IMG_1411

By the afternoon of the third day of framing the roof trusses were up and blocked, and all of the interior walls were braced and blocked.

 

More pics next week...


 

 

 
 
 