Kessler Woods Court Lot 28 SIP framing complete
Editorial Rating:
Two weeks after the structurally insulated panels were delivered the framing of the whole house is complete.
DAY 1 - SIPS DELIVERED The SIPs were manufactured by KORWALL which is located locally in Arlington Texas.
DAY 2 - SIPS BEING ERECTED The second day after the SIPs were delivered the framing crew is already going to work.
DAY 6 - ROOFS PANELS GOING ON The guest bedroom is beginning to take shape.
DAY 10 - GLULAM BEAMS INSTALLED The roof framing for the living, kitchen, and dining are being completed along with the floor joists for the second floor.
DAY 14 - SIPS COMPLETED Two weeks later and the whole house is framed up.
For more information on the development check out kesslerwoods
This page Copyright © LiveModern, Inc. and
by the Contributing Author(s) above, if any.
delcambre, j. (2007, April 29). Kessler Woods Court Lot 28 SIP framing complete. Retrieved November 20, 2008, from LiveModern: Your Best Modern Home Web site: http://livemodern.com/Members/jpd12arch/blog.2006-05-24.3707315713/blogentry.2007-04-29.3475939503.
This work is licensed under a Creative Commons License. Cite/Attribute Resource.
This work is licensed under a Creative Commons License. Cite/Attribute Resource.