Kessler Woods Court Lot 28 SIP framing complete

by jonathan delcambre posted on 04-29-2007 09:32 last modified 04-29-2007 09:32

Editorial Rating: 1 2 3 4 5 Reader Rating: 1 2 3 4 5 ( 0 votes)
Click to change your reader rating: (not rated)   worthless bad average good great
Two weeks after the structurally insulated panels were delivered the framing of the whole house is complete.

DAY 1 - SIPS DELIVERED The SIPs were manufactured by KORWALL which is located locally in Arlington Texas.

sips

DAY 2 - SIPS BEING ERECTED The second day after the SIPs were delivered the framing crew is already going to work.

day 2

DAY 6 - ROOFS PANELS GOING ON The guest bedroom is beginning to take shape.

day 6

DAY 10 - GLULAM BEAMS INSTALLED The roof framing for the living, kitchen, and dining are being completed along with the floor joists for the second floor.

day 10

DAY 14 - SIPS COMPLETED Two weeks later and the whole house is framed up.

day 14a

day 14b

day 14c

For more information on the development check out kesslerwoods

jonathandelcambre

This page Copyright © LiveModern, Inc. and by the Contributing Author(s) above, if any. delcambre, j. (2007, April 29). Kessler Woods Court Lot 28 SIP framing complete. Retrieved July 03, 2009, from LiveModern: Your Best Modern Home Web site: http://livemodern.com/Members/jpd12arch/blog.2006-05-24.3707315713/blogentry.2007-04-29.3475939503.